[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899356":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},899356,582,1,"单选题","（2017年考题）某施工合同约定人工工资为200元\u002F工日，窝工补贴按人工工资的25%计算，在施工过程中发生了如下事件：①出现异常恶劣天气导致工程停工2天，人员窝工20个工日；②因恶劣天气导致场外道路中断，抢修道路用工20个工日；③几天后，场外停电，停工1天，人员窝工10个工日。承包人可向发包人索赔的人工费为（ ）元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1500",false,{"key":16,"text":17,"correct":14},"B","2500",{"key":19,"text":20,"correct":21},"C","4500",true,{"key":23,"text":24,"correct":14},"D","5500","异常恶劣天气导致窝工，仅可索赔工期。抢修道路索赔=20×200=4000元；停电窝工索赔=10×200×25%=500。共计索赔4500元。参见教材P242。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]