[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899355":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},899355,582,1,"单选题","（2017年考题）关于施工过程中的现场签证，下列说法中正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","发包人应按照现场签证内容计算价款，在竣工结算时一并支付",false,{"key":16,"text":17,"correct":14},"B","没有计日工单价的现场签证，按承包商提出的价格计算并支付",{"key":19,"text":20,"correct":14},"C","因发包人口头指令实施的现场签证事项，其发生的费用应由发包人承担",{"key":22,"text":23,"correct":24},"D","经发包人授权的工程咨询人，可与承包人做现场签证",true,"合同工程发生现场签证事项，未经发包人签证确认，承包人便擅自实施相关工作的，除非征得发包人书面同意，否则发生的费用由承包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]