[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899345":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},899345,582,1,"单选题","（2020年真题）根据现行《标准设计施工总承包招标文件》，关于\"合同价格\"和\"签约合同价\"下列说法正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","合同价格是指签约合同价",false,{"key":16,"text":17,"correct":18},"B","签约合同价中包括了专业工程暂估价",true,{"key":20,"text":21,"correct":14},"C","合同价格不包括按合同约定进行的变更价款",{"key":23,"text":24,"correct":14},"D","签约合同价一般高于中标价","P220-228 《标准设计施工总承包招标文件》合同协议书中称合同价格为“签约合同价”，即指中标通知书明确的并在签订合同时于合同协议书中写明的，包括了暂列金额、暂估价的合同总金额，而\"合同价格\"是指承包人按合同约定完成了包括缺陷责任期内的全部承包工作后，发包人应付给承包人的金额，包括在履行合同过程中按合同约定进行的变更和调整。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]