[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899339":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},899339,582,1,"单选题","（2015年考题）关于世界银行贷款项目采用国际竞争性招标，下列说法中正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","借款人向世界银行送交总采购通告的时间，最晚不应迟于公开发售招标文件前90天",false,{"key":16,"text":17,"correct":14},"B","一个项目的具体采购合同是否需要资格预审，由借款人自主决定",{"key":19,"text":20,"correct":21},"C","未进行资格预审的，评标后应对标价最低并拟授予合同的投标人进行资格定审",true,{"key":23,"text":24,"correct":14},"D","招标文件公开发售前，无需得到世界银行的意见","如果未经资格预审，则应对评标价最低的投标人进行资格定审。定审结果，如果认定他有资格，又有足够的人力、财力资源承担合同任务，就应报送世界银行，建议授予合同。如发现他不符合要求，则再对评标价次低的投标人进行资格定审。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]