[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899334":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},899334,582,1,"单选题","（2019年考题）国际工程投标报价时，对于当地采购的材料，其单价应为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","市场价格+运杂费",false,{"key":16,"text":17,"correct":14},"B","市场价格+运杂费+运输保管耗损费",{"key":19,"text":20,"correct":14},"C","市场价格+运余费+采购保管费",{"key":22,"text":23,"correct":24},"D","市场价格+运杂费+采购保管费+运输保管损耗费",true,"国际工程投标报价时，当地采购的材料、设备单价的计算公式为：材料、设备单价=市场价格+运杂费+采购保管费+运输保管损耗费。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]