[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899330":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},899330,582,1,"单选题","（2020年真题）对于综合评估法中的评标基准价的确定，下列说法正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","按所有有效投标人中的最低投标价确定",false,{"key":16,"text":17,"correct":14},"B","按所有有效投标人的平均投标价确定",{"key":19,"text":20,"correct":14},"C","按所有有效投标人的平均投标价乘以事先约定的浮动系数确定",{"key":22,"text":23,"correct":24},"D","按项目特点、行业管理规定自行确定",true,"P213-217 评标基准价的计算方法应在投标人须知前附表中予以明确。招标人可依据招标项目的特点、行业管理规定给出评标基准价的计算方法，确定时也可适当考虑投标人的投标报价。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]