[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899319":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},899319,582,1,"单选题","（2017年考题）下列施工评标及相关工作事宜中，属于清标工作内容的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","投标文件的澄清",false,{"key":16,"text":17,"correct":14},"B","施工组织设计的评审",{"key":19,"text":20,"correct":14},"C","形式评审",{"key":22,"text":23,"correct":24},"D","不平衡报价分析",true,"清标工作主要包含下列内容:（1）对招标文件的实质性响应；（2）错漏项分析；（3）分部分项工程项目清单综合单价的合理性分析；（4）措施项目清单的完整性和合理性分析，以及其中不可竞争性费用正确分析；（5）其他项目清单完整性和合理性分析；（6）不平衡报价分析；（7）暂列金额、暂估价正确性复核；（8）总价与合价的算术性复核及修正建议；（9）其他应分析和澄清的问题。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]