[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899309":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},899309,582,1,"单选题","（2015年考题）关于投标报价，下列说法中正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","总价措施项目由投标人自主报价",false,{"key":16,"text":17,"correct":14},"B","暂列金额依据招标工程量清单总说明，结合项目管理规划自主填报",{"key":19,"text":20,"correct":14},"C","暂估价依据询价情况填报",{"key":22,"text":23,"correct":24},"D","投标人对投标报价的任何优惠均应反映在相应的清单项目的综合单价中",true,"投标人的投标总价应当与组成工程量清单的分部分项工程费、措施项目费、其他项目费和规费、税金的合计金额相一致，即投标人在进行工程量清单招标的投标报价时，不能进行投标总价优惠（或降价、让利），投标人对投标报价的任何优惠（或降价、让利）均应反映在相应清单项目的综合单价中。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]