[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899308":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},899308,582,1,"单选题","（2019年考题）在投标报价确定分部分项工程综合单价时，应根据所选的计算基础计算工程内容的工程量，该数量应为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","实物工程量",false,{"key":16,"text":17,"correct":14},"B","施工工程量",{"key":19,"text":20,"correct":21},"C","定额工程量",true,{"key":23,"text":24,"correct":14},"D","复核的清单工程量","在投标报价确定分部分项工程综合单价时，计算基础主要包括消耗量指标和生产要素单价。应根据本企业的实际消耗量水平，并结合拟定的施工方案确定完成清单项目需要消耗的各种人工、材料、施工机具台班的数量。因此，计算的工程量为定额工程量。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]