[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899306":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},899306,582,1,"单选题","（2018年考题）招标工程量清单中某分部分项清单项目与某一计价定额子目的工作内容与计量规则一致，则确定该清单项目综合单价不可或缺的工作是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","计算工程内容的工程数量",false,{"key":16,"text":17,"correct":14},"B","计算工程内容的清单单位含量",{"key":19,"text":20,"correct":14},"C","计算措施项目的费用",{"key":22,"text":23,"correct":24},"D","计算管理费、利润和风险费用",true,"当分部分项工程内容比较简单，由单一计价子项计价，且《建设工程工程量清单计价规范》GB 50500-2013与所使用计价定额中的工程量计算规则相同时， 微 信 公 众 号：金 考 典 ，新题，押 题！ 综合单价的确定只需用相应定额子目中的人、材、机费作为基数计算管理费、利润和风险费用。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]