[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899305":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},899305,582,1,"单选题","（2018年考题）关于工程施工投标报价过程中的工程量复核，下列说法正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","复核的准确程度不会影响施工方法的选用",false,{"key":16,"text":17,"correct":14},"B","复核的目的在于修改工程量清单中的工程量",{"key":19,"text":20,"correct":21},"C","复核有助于防止由于物资少***的停工待料",true,{"key":23,"text":24,"correct":14},"D","复核中发现的遗漏和错误应向招标人提出","A复核的准确程度会影响施工方法的选用；B复核的目的不是修改工程量清单，即使有误，投标人也不能修改工程量清单中的工程量，因为修改了清单将导致在评标时认为投标未响应招标文件而被否决。D针对清单中工程量的遗漏和错误，投标人可以运用一些报价的技巧提高报价的质量，争取在中标后能获得更大的收益。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]