[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899296":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},899296,582,1,"单选题","（2020年真题）关于最高投标限价的编制，下列说法正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","国有企业的建设工程招标可以不编制最高投标限价",false,{"key":16,"text":17,"correct":14},"B","招标文件中可以不公开最高投标限价",{"key":19,"text":20,"correct":14},"C","最高投标限价与标底的本质是相同的",{"key":22,"text":23,"correct":24},"D","政府投资的建设工程招标时，应设最高投标限价",true,"P190-195 国有资金投资的建筑工程招标的，应当设有最高投标限价；非国有资金投资的建筑工程招标的，可以设有最高投标限价或者招标标底。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]