[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899292":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},899292,582,1,"单选题","（2017年考题）关于招标工程量清单中其他项目清单的编制，下列说法中正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投标人情况、发包人对工程管理要求对其內容会有直接影响",false,{"key":16,"text":17,"correct":18},"B","暂列金额可以只列总额，但不同专业预留的暂列金额应分别列项",true,{"key":20,"text":21,"correct":14},"C","专业工程暂估价应包括利润、规费和税金",{"key":23,"text":24,"correct":14},"D","计日工的暂定数量可以由投标人填写","A选项，投标人情况对招标工程量清单内容无直接影响；C选项，以“项”为计量单位给出的专业工程暂估价一般应是综合暂估价，即应当包括除规费、税金以外的管理费、利润等；D选项计日工的暂定数量由招标人填写。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]