[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899283":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},899283,582,1,"单选题","（2019年考题）编制招标工程量清单时，应根据施工图纸的深度、暂估价设定的水平、合同价款约定调整因素以及工程实际情况合理确定的清单项目是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","措施项目清单",false,{"key":16,"text":17,"correct":18},"B","暂列金额",true,{"key":20,"text":21,"correct":14},"C","专业工程暂估价",{"key":23,"text":24,"correct":14},"D","计日工","在确定暂列金额时应根据施工图纸的深度、暂估价设定的水平、合同价款约定调整的因素以及工程实际情况合理确定。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]