[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899280":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},899280,582,1,"单选题","（2018年考题）关于施工招标文件的疑问和澄清，下列说法正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","投标人可以口头方式提出疑问",false,{"key":16,"text":17,"correct":14},"B","投标人不得在投标截止前的15天内提出疑问",{"key":19,"text":20,"correct":14},"C","投标人收到澄清后的确认时间应按绝对时间设置",{"key":22,"text":23,"correct":24},"D","招标文件的书面澄清应发给所有投标人",true,"选项AB错误，投标人可以书面方式提出疑问。招标文件的澄清将在规定的投标截止时间15天前以书面形式发给所有购买招标文件的投标人，但不指明澄清问题的来源。选项C错误，投标人收到澄清后的确认时间应按相对时间设置。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]