[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899279":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},899279,582,1,"单选题","（2018年考题）直接发承包项目如按初步设计总概算投资包干，其签约合同费应以（ ）为准。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","经审批的概算投资总额",false,{"key":16,"text":17,"correct":14},"B","经审批的概算投资中与承包内容相对应的建筑安装费用",{"key":19,"text":20,"correct":21},"C","经审批的概算投资中与承包内容相对应部分的投资",true,{"key":23,"text":24,"correct":14},"D","经审批的概算投资汇总相对应的工程费","对于招标发包的项目：应以中标时确定的金额为准；对于直接发包的项目，如按照初步设计总概算投资包干时，应以经审批的概算投资中与承包内容相应部分的投资（包括相应的不可预见费）为签约合同价；如施工图预算包干，则应以审查后的施工图总预算或综合预算为准",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]