[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899264":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},899264,582,1,"单选题","（2017年考题）根据《建设工程工程量清单计价规范》（GB50500-2013），招标控制价的综合单价组价工作包括：①确定工、料、机单价；②确定所组价定额项目名称；③计算组价定额项目的合价；④除以工程量清单项目工程量；⑤计算组价定额项目工程量，下列工作排序正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","②⑤①③④",true,{"key":16,"text":17,"correct":18},"B","①②⑤④③",false,{"key":20,"text":21,"correct":18},"C","②③①⑤④",{"key":23,"text":24,"correct":18},"D","①②③④⑤","工料单价法编制施工图预算程序：准备工作→划分工程项目和计算工程量→套用工料单价→计算措施项目人材机费→工料分析→计算主材费并调整直接费→按费用定额取费→汇总造价。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]