[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899251":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},899251,582,1,"单选题","（2016年考题）下列原因中，不能据以调整设计概算的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","超出原设计范围的重大变更",false,{"key":16,"text":17,"correct":18},"B","超出承包人预期的货币贬值和汇率变化",true,{"key":20,"text":21,"correct":14},"C","超出基本预备费规定范围的不可抗拒重大自然灾害引起的工程变动和费用增加",{"key":23,"text":24,"correct":14},"D","超出价差预备费的国家重大政策性调整","本题考查的是设计概算的概念及其编制内容。允许调整概算的原因包括以下几点：（1）超出原设计范围的重大变更；（2）超出基本预备费规定范围不可抗拒的重大自然灾害引起的工程变动和费用增加；（3）超出工程遭际价差预备费的国家重大政策性的调整。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]