[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899248":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},899248,582,1,"单选题","（2015年考题）设计概算一经批准一般不得进行调整，其总投资应反映（ ）时的价格水平。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目立项",false,{"key":16,"text":17,"correct":14},"B","可行性研究",{"key":19,"text":20,"correct":21},"C","概算编制",true,{"key":23,"text":24,"correct":14},"D","项目施工","设计概算编制时应满足以下要求：1）设计概算应按编制时项目所在地的价格水平编制，总投资应完整地反映编制时建设项目实际投资;2）设计概算应考虑建设项目施工条件等因素对投资的影响;3）设计概算应按项目合理建设期限预测建设期价格水平，以及资产租赁和贷款的时间价值等动态因素对投资的影响。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]