[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899242":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},899242,582,1,"单选题","（2016年考题）某地拟建一工程，与其类似的已完工程单方工程造价为4500元\u002Fm3，其中人、材料、施工机具使用费分别占工程造价的15%、55%和10%，拟建工程地区与类似工程地区人工、材料、施工机具使用费差异系数分别为1.05、1.03和0.98。假定以人、材、机费用之和为基数取费，综合费率为25%。用类似工程预算法计算的拟建工程造价指标为（ ）元\u002Fm2。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3699.00",false,{"key":16,"text":17,"correct":14},"B","4590.75",{"key":19,"text":20,"correct":14},"C","4599.00",{"key":22,"text":23,"correct":24},"D","4623.75",true,"本题考查的是设计概算的编制。 直接费：4500*（0.15+0.55+0.1）=3600. 人工费占直接费比：4500*0.15\u002F3600=0.1875 材料费占直接费比：4500*0.55\u002F3600=0.6875 机械费占直接费比：4500*0.1\u002F3600=0.125 K=0.1875×1.05+0.6875×1.03+0.125×0.98=1.0275；3600×1.0275×1.25=4623.75 元\u002F㎡",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]