[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899240":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},899240,582,1,"单选题","（2018年考题）采用概算定额法编制设计概算的主要工作有：①列出分部分项工程项目名称并计算工程量；②搜集基础资料；③编制概算和编制说明；④计算措施项目费；⑤确定各分部分项工程费；⑥汇总单位工程概算造价。下列工作排序正确的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","②①⑤④⑥③",true,{"key":16,"text":17,"correct":18},"B","②③①⑤④⑥",false,{"key":20,"text":21,"correct":18},"C","③②①④⑤⑥",{"key":23,"text":24,"correct":18},"D","②①③⑤④⑥","概算定额法编制设计概算的步骤：1.搜集基础资料；2.列出分部分项工程项目名称并计算工程量;3.确定各分部分项工程费;4.计算措施项目费;5.汇总单位工程概算造价6.编写概算编制说明",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]