[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899225":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},899225,582,1,"单选题","（2017年考题）在国外其地建设一座化工厂，已知设备到达工地的用 （E）为3000万美元，该项目的朗格系数（K）及包含的內容如下表所示。则该工厂的同接费用为（ ）万美元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","9009",false,{"key":16,"text":17,"correct":14},"B","6930",{"key":19,"text":20,"correct":21},"C","2079",true,{"key":23,"text":24,"correct":14},"D","1350","该厂的间接费用=3000×1.4×1.1×1.5×0.3=2079万美元。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]