[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899216":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},899216,582,1,"单选题","（2017年考题）关于我国项目前期阶段投资估算的精度要求下列说法中正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目建议书阶段，允许误差大于±30%",false,{"key":16,"text":17,"correct":14},"B","投资设想阶段，要求误差控制在±30%以內",{"key":19,"text":20,"correct":21},"C","预可行性研究阶段，要求误差控制在±20%以內",true,{"key":23,"text":24,"correct":14},"D","可行性研究阶段，要求误差控制在±15%以內","A选项应在±30%以內；B选项为国外做法；D选项应在±10%以內。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]