[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899215":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},899215,582,1,"单选题","（2017年考题）关于项目投资估算的作用，下列说法中正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目建议书阶段的投资估算，是确定建设投资最高限额的依据",false,{"key":16,"text":17,"correct":14},"B","可行性研究阶段的授资估算，是项目投资决策的重要依据，不得突破",{"key":19,"text":20,"correct":14},"C","投资估算不能作为制定建设货款计划的依据",{"key":22,"text":23,"correct":24},"D","投资估算是核算建设项目固定资产需要数的重要依据",true,"A、B错：当可行性研究报告被批准后，其技资估算额将作为设计任务书中下达的投资限额，即建设项目投资的最高限额，不能随意突破。C错：项目投资估算可作为项目资金筹措及制订建设贷款计划的依据，建设单位可根据批准的项目投资估算额，进行资金筹措和向银行申请贷款。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]