[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899192":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},899192,582,1,"单选题","（2020年真题）关于概算定额，下列说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不仅包括人工、材料和施工机具台班的数量标准，还包括费用标准",true,{"key":16,"text":17,"correct":18},"B","是施工定额的综合与扩大",false,{"key":20,"text":21,"correct":18},"C","反映的主要内容、项目划分和综合扩大程度与预算定额类似",{"key":23,"text":24,"correct":18},"D","定额水平体现平均先进水平","P76-84 概算定额是在预算定额基础上，确定完成合格的单位扩大分项工程或单位扩大结构构件所需消耗的人工、材料和施工机具台班的数量标准及其费用标准。概算定额表达的主要内容、表达的主要方式及基本使用方法都与预算定额相近。概算定额与预算定额的不同之处，在于项目划分和综合扩大程度上的差异。概算定额应该贯彻社会平均水平和简明适用的原则。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]