[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899175":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},899175,582,1,"单选题","（2016年考题）某出料容量750L的砂浆搅拌机，每一次循环工作中，运料、装料、搅拌、卸料、终端需要的时间分别为150s、40s、250s、50s、40s，运料和其他时间的交叠时间为50s，机械利用系数为0.8。该机械的台班产量定额为（ ）m3\u002F台班。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","29.79",false,{"key":16,"text":17,"correct":14},"B","32.60",{"key":19,"text":20,"correct":21},"C","36.00",true,{"key":23,"text":24,"correct":14},"D","39.27","本题考查的是确定材料定额消耗量的基本方法。一次循环的正常延续时间=150+40+250+50+40-50=480s；每一小时循环次数=3600\u002F480=7.5（次）；一小时正常生产率=7.5*750=5.625（m3）；产量定额=5.625*8*0.8=36.00（m3\u002F台班），",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]