[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899170":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},899170,582,1,"单选题","（2016年考题）若完成1m3墙体砌筑工作的基本工时为0.5工日，辅助工作时间占工序时间的4%，准备与结束工作时间、不可避免的中断时间、休息时间分别占工作时间的6%、3%和12%，该工程时间定额为（ ）工日\u002Fm3。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","0.581",false,{"key":16,"text":17,"correct":14},"B","0.608",{"key":19,"text":20,"correct":14},"C","0.629",{"key":22,"text":23,"correct":24},"D","0.659",true,"本题考查的是确定人工定额消耗量的基本方法。工序作业时间=0.5\u002F（1-4%）=0.521（工日\u002Fm3），时间定额=0.521\u002F（1-6%-3%-12%）=0.659（工日\u002Fm3）",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]