[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899167":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},899167,582,1,"单选题","（2020年真题）关于分部分项工程项目清单中项目编码的编制，下列说法正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","第二级编码为分部工程顺序码",false,{"key":16,"text":17,"correct":14},"B","第五级编码为分项工程项目名称顺序码",{"key":19,"text":20,"correct":14},"C","同一标段内多个单位工程中项目特征完全相同的分项工程，可采用相同编码",{"key":22,"text":23,"correct":24},"D","补充项目应采用6位编码工程",true,"P44-47 A选项错误：第二级编码为附录分类顺序码 B选项错误：第五级编码为工程量清单项目名称顺序码 C选项错误：同一招标工程的项目不得重码. D选项正确：补充项目的编码由工程量计算规范的代码与B和三位阿拉伯数字组成，并应从001起顺序编制，例如房屋建筑与装饰工程如需补充项目，则其编码应从01B001开始起顺序编制，同一招标工程的项目不得重码.",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]