[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899163":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},899163,582,1,"单选题","（2015年考题）关于工程量清单的编制，下列说法中正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目编码以五级全国统一编码设置，用十二位阿拉伯数字表示",false,{"key":16,"text":17,"correct":14},"B","编制分部分项工程量清单时，必须对工作内容进行描述",{"key":19,"text":20,"correct":21},"C","补充项目的编码由计量规范的代码与B和三位阿拉伯数字组成",true,{"key":23,"text":24,"correct":14},"D","按施工方案计算的措施费，必须写明“计算基础”、“费率”的数值","补充项目的编码应按计量规范的规定确定。具体做法如下：补充项目的编码由计量规范的代码与B和三位阿拉伯数字组成，并应从001起顺序编制，例如房屋建筑与装饰工程如需补充项目，则其编码应从01B001开始起顺序编制，同一招标工程的项目不得重码。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]