[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899159":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},899159,582,1,"单选题","（2017年考题）根据《建设工程工程量清单计价规范》（GB50500-2013），一般不作为安全文明施工费计算基础的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","定额人工费",false,{"key":16,"text":17,"correct":18},"B","定额人工费+定额材料费",true,{"key":20,"text":21,"correct":14},"C","定额人工费+定额施工机具使用费",{"key":23,"text":24,"correct":14},"D","定额人工费+定额施工机具使用费+定额材料费","\"计算基础\"中安全文明施工费可为\"定额基价\"、\"定额人工费\"或\"定额人工费+定额施工机具使用费\"，其他项目可为\"定额人工费\"或\"定额人工费+定额施工机具使用费\"。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]