[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899155":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},899155,582,1,"单选题","（2020年真题）下列工程量清单计价的基本原理描述正确的是（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","∑分部分项工程量×工料单价",false,{"key":16,"text":17,"correct":14},"B","∑措施项目工程量×措施项目工料单价）",{"key":19,"text":20,"correct":21},"C","其他项目=暂列金额+暂估价+计日工+总承包服务费",true,{"key":23,"text":24,"correct":14},"D","单项工程费=分部分项项目费+措施项目费+其他项目+税金","P37-39 分部分项工程费=∑（分部分项工程量x相应分部分项工程综合单价）； 措施项目费=∑各措施项目费； 其他项目费=暂列金额+暂估价+计日工+总承包服务费 单位工程造价=分部分项工程费+措施项目费+其他项目费+规费+税金； 单项工程造价=∑单位工程造价； 建设项目总造价=∑单项工程造价。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]