[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899154":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},899154,582,1,"单选题","（2018年考题）根据《建设工程工程量计价规范》（GB 50500-2013，关于工程量清单编制和计价，下列说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","暂列金额由招标人在工程量清单中暂定",true,{"key":16,"text":17,"correct":18},"B","暂列金额包括暂不能确定价格的材料暂定价",false,{"key":20,"text":21,"correct":18},"C","专业工程量暂估价中包括规费和税金",{"key":23,"text":24,"correct":18},"D","计日工单价中不包括企业管理费和利润","本题考查的是其他项目清单。招标人在工程量清单中暂定并包括在合同价款中的一笔款项。用于工程合同签定时尚未确定或者不可预见的所需材料、工程设备、服务的采购，施工中可能发生的工程变更、合同约定调整因素出现时的合同价款调整以及发生的索赔、现场签证确认等的费用。专业工程暂估价中不包括规费和税金。计日工单价中包括企业管理费和利润。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]