[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899153":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},899153,582,1,"单选题","（2018年考题）反应完成一定计量单位合格扩大结构构件需要消耗的人工、材料和施工机具台班的数量的定额是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","概算指标",false,{"key":16,"text":17,"correct":18},"B","概算定额",true,{"key":20,"text":21,"correct":14},"C","预算定额",{"key":23,"text":24,"correct":14},"D","施工定额","本题考查的是工程定额的分类。概算定额是完成单位合格扩大分项工程或扩大结构构件所需消耗的人工、材料和施工机具台班的数量及其费用标准。概算指标是以单位工程为对象，反应完成一个规定计量单位建筑安装产品的经济指标。预算定额是在正常的施工条件下，完成一定计量单位和各分项工程或结构构件所需消耗的人工、材料、施工机具台班数量及其费用标准。施工定额是完成一定计量单位的某一施工过程或基本工序所需消耗的人工、材料和施工机具台班数量标准。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]