[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899148":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},899148,582,1,"单选题","（2019年考题）在工程量清单计价中下列关于暂估价的说法正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","材料设备暂估价是指用于尚未确定或不可预见的材料、设备采购的费用",false,{"key":16,"text":17,"correct":14},"B","纳入分部分项工程项目清单综合单价中的材料暂估价包括暂估单价及数量",{"key":19,"text":20,"correct":21},"C","专业工程暂估价与分部分项工程综合单价在费用构成方面应保持一致",true,{"key":23,"text":24,"correct":14},"D","专业工程暂估价由投标人自主报价","专业工程的暂估价一般应是综合暂估价，包括人工费、材料费、施工机具使用费、企业管理费和利润，不包括规费和税金。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]