[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899144":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},899144,582,1,"单选题","（2019年考题）根据现行工程量计算规范，适宜采用分部分项工程项目清单计价方式计价的措施项目费是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","二次搬运费",false,{"key":16,"text":17,"correct":18},"B","超高施工增加费",true,{"key":20,"text":21,"correct":14},"C","已完工程及设备保护费",{"key":23,"text":24,"correct":14},"D","地上、地下设施临时保护费","有些措施项目则是可以计算工程量的项目，如脚手架工程，混凝土模板及支架（撑），垂直运输，超高施工增加，大型机械设备进出场及安拆，施工排水、降水等，这类措施项目按照分部分项工程项目清单的方式，采用综合单价计价，更有利于措施费的确定和调整。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]