[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899139":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},899139,582,1,"单选题","（2017年考题）下列计价性定额中，项目划分最细的计价定额是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","材料消耗定额",false,{"key":16,"text":17,"correct":14},"B","劳动定额",{"key":19,"text":20,"correct":21},"C","预算定额",true,{"key":23,"text":24,"correct":14},"D","概算定额","C、D选项为计价性定额，预算定额项目划分更为详细。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]