[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899135":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},899135,582,1,"单选题","（2020年真题）下列计入总价措施项目表的是（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","垂直运输费",false,{"key":16,"text":17,"correct":14},"B","施工降排水",{"key":19,"text":20,"correct":21},"C","地上地下成品保护",true,{"key":23,"text":24,"correct":14},"D","大型机械进出场","P15-20 不宜计量的措施项目。对于不宜计量的措施项目，通常用计算基数乘以费率的方法予以计算。 1）安全文明施工费。 2）其余不宜计量的措施项目。包括夜间施工增加费，非夜间施工照明费，二次搬运费，冬雨季施工增加费，地上、地下设施、建筑物的临时保护设施费，已完工程及设备保护费等。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]