[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899081":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},899081,582,1,"单选题","（2018年考题）根据现行建设项目投资相关规定，固定资产投资应与（ ）相对应。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程费用+工程建设其他费用",false,{"key":16,"text":17,"correct":18},"B","建设投资+建设期利息",true,{"key":20,"text":21,"correct":14},"C","建设安装工程费+设备及工器具购置费",{"key":23,"text":24,"correct":14},"D","建设项目总投资","本题考查的是建设工程造价构成。生产性建设项目总投资包括建设投资、建设期利息和流动资金三部分；非生产性建设项目总投资包括建设投资和建设期利息两部分。其中建设投资和建设期利息之和对应于固定资产投资。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]