[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899063":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},899063,582,1,"单选题","关于计算新增固定资产的表述，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","为了保护环境而正在建设的附属工程随主体工程计入新增固定资产价值",false,{"key":16,"text":17,"correct":18},"B","不构成生产系统但能独立发挥效益的非生产性项目，在交付使用后计入新增固定资产价值",true,{"key":20,"text":21,"correct":14},"C","达到固定资产标准不需安装的设备，购买后计入新增固定资产价值",{"key":23,"text":24,"correct":14},"D","分批交付生产的工程，应待全部交付完毕后一次性计入新增固定资产价值","2020版教材P307 （2）对于单项工程中不构成生产系统，但能独立发挥效益的非生产性项目，如住宅、食堂、医务所、托儿所、生活服务网点等，在建成并交付使用后，也要计算新增固定资产价值。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]