[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899047":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},899047,582,1,"单选题","《标准设计施工总承包招标文件》中提供的 (A) (B)条款较多，其中暂估价的 (B)条款适用于（ ）的约定。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","合同价格中不包括暂估价",false,{"key":16,"text":17,"correct":18},"B","签约合同价中包括暂估价",true,{"key":20,"text":21,"correct":14},"C","签约合同价中不包括暂估价",{"key":23,"text":24,"correct":14},"D","合同价格中包括暂估价","暂估价(B) 条款，签约合同价中包括暂估价的，按合同约定进行支付，不予调 整价差。2020教材P274-280",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]