[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899043":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},899043,582,1,"单选题","根据《建标准设计施工总承包招标文件》2012年规定，变更程序不包括（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","变更的提出",false,{"key":16,"text":17,"correct":14},"B","变更估价",{"key":19,"text":20,"correct":21},"C","反索赔",true,{"key":23,"text":24,"correct":14},"D","变更指示","2020版教材P275 变更程序包括变更的提出，变更估价和变更指示。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]