[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899041":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},899041,582,1,"单选题","根据FIDIC施工合同条件，如果没有可供参考的相关费率或价格，则新的费率或价格应根据实施该项工作的合理费用，以及合同专用条款中规定的利润率计取，如果没有规定的利润率，则按（ ）计取",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5%",true,{"key":16,"text":17,"correct":18},"B","3%",false,{"key":20,"text":21,"correct":18},"C","10%",{"key":23,"text":24,"correct":18},"D","1%","2020版教材P282 如果没有可供参考的相关费率或价格，则新的费率或价格应根据实施该项工作的合理费用，以及合同专用条款中规定的利润率计取，如果没有规定的利润率，则按5%计取",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]