[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899039":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},899039,582,1,"单选题","关于质量保证金的使用及返还，下列说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不实行国库集中支付的政府投资项目，保证金可以预留在财政部门",true,{"key":16,"text":17,"correct":18},"B","采用工程质量保险担保的，发包人仍可预留5％的保证金",false,{"key":20,"text":21,"correct":18},"C","非承包人责任的缺陷，承包人仍有缺陷修复的义务",{"key":23,"text":24,"correct":18},"D","缺陷责任期终止后的28天内，发包人应将剩余的质量保证金连同利息返还给承包人","本题考查的是质量保证金的使用及返还。缺陷责任期内，实行国库集中支付的政府投资项目，保证金的管理应按国库集中支付的有关规定执行。其他政府投资项目，保证金可以预留在财政部门或发包方。选项B错误，采用工程质量保证担保、工程质量保险等其他方式的，发包人不得再预留质量保证金。选项C错误，由他人及不可抗力原因造成的缺陷，发包人负责组织维修，承包人不承担费用，且发包人不得从质量保证金中扣除费用。选项D错误，在合同约定的缺陷责任期终止后的14天内，发包人应将剩余的质量保证金返还给承包人。2020教材P262-263",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]