[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899017":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},899017,582,1,"单选题","由于发包人原因导致工程无法按规定期限进行竣（交）工验收的，关于其缺陷责任期的起点，说法正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","自工程实际竣（交）工之日算起",false,{"key":16,"text":17,"correct":14},"B","自承包人提交竣（交）工验收报告之日算起",{"key":19,"text":20,"correct":14},"C","自承包人提交竣（交）工验收申请之日算起",{"key":22,"text":23,"correct":24},"D","自承包人提交竣（交）工验收报告90天后，自动进入缺陷责任期",true,"2020版教材P262 缺陷责任期的期限。缺陷责任期从工程通过竣工验收之日起计。由于承包人原因导致工程无法按规定期限进行竣工验收的，缺陷责任期从实际通过竣工验收之日起计。由于发包人原因导致工程无法按规定期限进行竣工验收的，在承包人提交竣工验收报告90天后，工程自动进入缺陷责任期。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]