[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898989":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898989,582,1,"单选题","工程预付款起扣点表示（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","未施工工程尚需的主要材料及构件的价值相当于工程预付款数额",true,{"key":16,"text":17,"correct":18},"B","已施工工程尚需的主要材料及构件的价值相当于工程预付款数额",false,{"key":20,"text":21,"correct":18},"C","未施工工程尚需工程款相当于预付款数额",{"key":23,"text":24,"correct":18},"D","已施工工程尚需工程款相当于预付款数额","2020版教材P256 本题考查的是预付款及期中支付。预付款起扣点表示从未施工工程尚需的主要材料及构件的价值相当于工程预付款数额。预付款起扣点=承包工程合同总额-预付款总额／主要材料及构件所占比重。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]