[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898979":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898979,582,1,"单选题","某承包工程总价为500万元，其中材料费占45％，该工程计划工期为500天，材料储备定额天数为60天，则应支付预付款（ ）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","36.99",false,{"key":16,"text":17,"correct":14},"B","225",{"key":19,"text":20,"correct":21},"C","27",true,{"key":23,"text":24,"correct":14},"D","60","2020版教材P256 年度工程总价应为500\u002F500*365=365万元，答案应为500*45%*60\u002F365=27万元。@##",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]