[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898976":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898976,582,1,"单选题","某工程施工合同约定采用价格指数法调整合同价款，各项费用权重及价格如下表所示。已知该工程9月份完成的工程合同价款为3000万元，则9月份合同价款调整金额为()万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","22.5",false,{"key":16,"text":17,"correct":14},"B","61.46",{"key":19,"text":20,"correct":14},"C","75",{"key":22,"text":23,"correct":24},"D","97.5",true,"合同价款调整额=3000×(0.25×110／100+0.15×4200／4000+0.6-1)=97.5(万元)。2020教材P241-244",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]