[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898974":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898974,582,1,"单选题","某工程合同价格为5000万元，计划工期是200天，施工期间因非承包人原因导致工期延误10天，若同期该公司承揽的所有工程合同总价为2.5亿元，计划总部管理费为1250万元，则承包人可以索赔的总部管理费为()万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7.5",false,{"key":16,"text":17,"correct":14},"B","10",{"key":19,"text":20,"correct":21},"C","12.5",true,{"key":23,"text":24,"correct":14},"D","15","选项C正确。2020教材P245-253",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]