[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898972":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898972,582,1,"单选题","根据《标准施工招标文件》(2007年版)，下列事件中，既可索赔工期又可索赔费用的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","承包人提前竣工",false,{"key":16,"text":17,"correct":14},"B","提前向承包人提供工程设备",{"key":19,"text":20,"correct":21},"C","施工中遇到不利物质条件",true,{"key":23,"text":24,"correct":14},"D","异常恶劣的气候条件导致工期延误","根据《标准施工招标文件》(2007年版)，选项A、B只能索赔费用；选项C既可索赔工期，又可索赔费用；选项D只能索赔工期。2020教材P245-253",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]