[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898970":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898970,582,1,"单选题","施工合同履行期间，关于计日工费用的处理，下列说法中正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","已标价工程量清单中无某项计日工单价时，应按工程变更有关规定商定计日工单价",true,{"key":16,"text":17,"correct":18},"B","承包人通知发包人以计日工方式实施的零星工作，双方应按计日工方式予以结算",false,{"key":20,"text":21,"correct":18},"C","现场签证的计日工数量与招标工程量清单中所列不同时，应按工程变更有关规定进行价款调整",{"key":23,"text":24,"correct":18},"D","施工各期间发生的计日工费用应在竣工结算时一并支付","本题考查的是工程变更类合同价款调整事项。承包人应按照确认的计日工现场签证报告核实该类项目的工程数量，并根据核实的工程数量和承包人已标价工程量清单中的计日工单价计算，提出应付价款；已标价工程量清单中没有该类计日工单价的，由发承包双方按工程变更的有关的规定商定计日工单价计算。选项A正确，选项C错误。选项B错误，应为发包人通知承包人；选项D错误，应与进度款同期支付。2020教材P237-241",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]